Drucken

Patch Set 7 für Oracle Primavera Risk Analysis 8.7

Ein neues Patch Set für Oracle Primavera Risk Analysis 8.7 ist im My Oracle Support zum Download verfügbar. Das Patch Set enthält die Patches aus den vorhergehenden Patch Sets und ist ein vollständiges Installerpaket.

Issues Resolved in 8.7 PatchSet7

Bug ID

Title

19950382

INTERMITTENT ERROR CONNECTING TO P6: FAILED TO CALL EXPORTPROJECTPORTFOLIOS

19920008

PCF P80 COST DIFFERENT FROM DISTRIBUTION GRAPH WITH INSUFFICIENT ITERATIONS.

19896869

RUSSIAN CHARACTERS DISPLAYED INCORRECTLY IN PROJECT SELECTION SCREEN FOR EPS

19386472

CRASH WHEN ATTEMPTING TO DISPLAY PROBABILISTIC CASH FLOW INCLUDING NEGATIVE COST

19294314

LINK BETWEEN TASK & RISK NOT CREATED DURING IMPORT IF TASK ID USES LOWER CASE

19069661

EXPORT .MPP ERROR "MICROSOFT PROJECT ONLY SUPPORTS ONE LINK BETWEEN TWO TASKS"

18421694

"SHOW CUSTOM DATA..." HAS A DATA/FIELD LIMIT THAT DOES NOT ALLOW EDITING

18028831

DECIMAL CAN INITIALLY BE ENTERED AS QUANTITATIVE PROBABILITY

17212089

ERROR "FAILED TO OPEN DOCUMENT" WHEN OPENING PLAN

16827751

RISK SCORING REPORT KEY IS INCORRECT

16597524

UNDO RESOURCE ASSIGNMENT CHANGE DOES NOT RESET BUDGET VALUES

16597488

RUNTIME ERROR WHEN OPENING PRA PLAN DIRECTLY

16589275

USING THE @DATE FUNCTION IN A CALCULATED COLUMN RETURNS 'ERROR'.

16323761

NEGATIVE LAGS ARE IMPORTED INCORRECTLY FROM MSP WITH QUARTER HOUR PLANNING UNIT.

16323240

.PLNX EXPORT IMPORT DOES NOT RETAIN NON-WORKING CALENDER, PLANNING UNIT =HOUR

14613141

WHEN ASSIGNING BETAPERT DISTRIBUTION TO RESOURCE, TAKES UNIFORM SHAPE

14382613

SCHEDULE CHECK AND SRR DO NOT LOAD ON COMPUTER WITH RUSSIAN REGIONAL SETTINGS

13688149

THE P6 IMPORT OPTION TO USE SETTINGS FOR ALL USERS DOESN'T WORK

12908012

DURATION DISTRIBUTION FIGURES FROM P6 NOT CALCULATED AGAINST TIME PERIODS

12796681

EXCEPTIONS ADDED TO WEATHER CALENDAR

12361266

CANNOT EDIT RISK SENSITIVITY IN TORNADO

8956695

CHANGING TASK NAME DOES NOT REFRESH CORRELATED TASK EXISTENCES

 

Issues Resolved in 8.7 SP6

!---->

The following Oracle Support issues were resolved in 8.7 SP6. Click on either the ID or title to access the entire document from the Oracle Support site.

Bug ID

Title

8960018

'THERE WAS A PROBLEM WITH THE XML TRANSFORMATION' WHEN REPORTING ON LARGE PLAN

9179213

WBS RENUMBERED WHEN IMPORTING XER

13345948

CONSTRAINTS NOT IMPORTED FROM P6 PROFESSIONAL 8.1

13530110

PRA CREATES DUPLICATE IDS FROM ROLES IN P6, CAUSES CRASH FOR XER IMPORT

13910212

MILESTONES NOT IMPORTED FROM P6 R8 PROFESSIONAL

13921688

RESOURCE DISTRIBUTION IMPORTED AS UDF APPLIED TO MULTIPLE TASKS

14082039

DURATION DISTRIBUTION FIGURES ROUNDED TO NEAREST DAY UPON IMPORT FROM MSP

14387817

CREATE COST LOADING MATRIX NOT OPENING IN EXCEL

14406025

RESOURCE DISTRIBUTIONS DUPLICATED UPON IMPORT TO PRIMAVERA RISK ANALYSIS FROM P6

14532163

LINK BETWEEN TASK & RISK LOST AFTER IMPORT IF "PREFIX TASK ID" OPTION SELECTED

14698757

WBS STRUCTURE DOES NOT IMPORT FROM P6 PPPM 8.2 VIA API

14768367

HAMMOCK / LEVEL OF EFFORT ACTIVITIES ARE NOT IMPORTED FROM P6 8.2 PROFESSIONAL

14786218

PRA CRASH WHEN ASSIGNING RISKS TO TASKS IN RISK REGISTER AFTER IMPORT FROM P6

14840199

WEB SERVICES CAN NOT BE CONFIGURED FOR HTTPS/SSL, CORRECTION TO HELP IS NEEDED

15844695

SLOW IMPORT TIMES VIA API CONNECTION

15986983

CALENDAR EXCEPTIONS NOT IMPORTED FROM MSP 2010

16276910

PRA CRASHES WHEN OPENING PLAN AFTER DELETING SUB RESOURCE AND SAVING

16291522

'OUT OF MEMORY' ERROR RECEIVED WHEN ATTEMPTING TO IMPORT LARGE XER

16291928

ERROR: "METHOD CP3EJLINK::GETRISKISTERREGDATA FAILED" WHEN IMPORTING VIA API